We look forward to sharing with you the work that is completed through our Home run for the Future project. Check back often as we update this page with the work being done to bring the district its first-ever baseball and softball complex.
August/September 2025
Dirt work has begun at the site of the softball/baseball complex (just east of Clinton High School). Image 1 is from the front of the project looking towards the outfield. Image 2 is taken from the back of the project site toward home plate (you can see the high school in the distance). A lot of dirt has been moved to level the site and also create drainage that goes around the outside of the field.
.png)
.png)
September 2025
Dirt work continues and the pits have been dug for the dugouts.


October 2025
Dirt work continues. Dugouts and concession stand construction has started.



November 2025
Click here to view drone footage captured in mid-November showing the following construction progress:
- Footings for the concession stand being built
- Finished stonework on both dugouts
- Batting cage under construction
- Outfield fencing complete
- Lights being installed
- Trenches for electrical lines powering the lights
December 2025
Both dugout floorings have been poured and finished, the fence piping has been installed from the dugouts on to the rest of the field, and the excavation company is laying the drains for the field.


January 2026
Click here to view drone footage captured on January 7th showing the following construction progress:
- The white you see on the field is the rock base that will sit under the turf, meaning the turf will be installed very soon!
- Both dugouts are nearly finished.
- Batting cages have been poured and are ready for turf and netting.
- Work is starting on the concession stand/restrooms/press box.
- Following turf installation, the walls around home plate will be finished, field netting will be added, and spectator seating will be installed.
February 2026
Turf is being laid on the new field.